The Utah Department of Transportation (UDOT), in coordination with Tooele City, is designing the full pavement reconstruction of SR-36 from 3 O’Clock Drive to 1280 North and pavement rehabilitation (rotomill and overlay) from 1280 North to Stansbury Parkway. Click here to watch the project video.
The design phase will continue through early 2015. We anticipate construction will begin in late May. Paving north of 520 South will be complete by the end of 2015 and paving south of 520 South will be completed in early 2016. We’ll provide additional information as the design phase progresses. Once a contractor is selected in mid-April, we’ll be able to provide additional details on construction.
3 O’Clock Drive to 1280 North
- Remove and replace entire pavement section
- Install new storm drain
- Replace deficient curb, gutter and sidewalk
- Upgrade pedestrian ramps to meet ADA standards
- Complete utility work to accommodate road work
- Tooele City’s waterline replacement project from old Canyon Road to 600 North (this work will take place prior to the road reconstruction)
1280 North to 2000 North
- Remove and replace the top 1″ of pavement
- Install curb and gutter on east side of road
- Construct drainage improvements on east side of road
2000 North to Stansbury Parkway
- Remove and replace the top 1″ of pavement
|